Water System Upgrades

Water Bond Improvement Project List:


  

PROJECT UPDATES:

 
    Jackson Oaks, Main Avenue and Boys Ranch Wells Projects: 9-29-16 - Production wells are constructed. Designs nearing 90% completion.
    Oak Canyon Booster Station Project: 9-29-16 - 40% complete, block building complete, roof being installed. Project Photos   Schedule, plans.
     East Dunne Avenue Water Reservoir Project: 9-29-16 - Design 75% complete.
    East Dunne Avenue Booster Station Project: 9-29-16 - Design 40% complete.
 