Water System Upgrades

Water Bond Improvement Project List:


  

PROJECT UPDATES:

 
    Jackson Oaks, Main Avenue and Boys Ranch Wells Projects: 2-20-17 - Production wells are constructed. Designs nearing 98% completion. Out to bid in February 2017.
     Oak Canyon Booster Station Project: 2-20-17 - 82% complete, installing new pumps, electronics and roof. Project Photos   Schedule, plans.
     East Dunne Avenue Water Reservoir Project: 2-20-17 - Design 85% complete. Environmental studies almost complete.
     East Dunne Avenue Booster Station Project: 2-20-17 - Design 50% complete.
 


Community Meetings:


Jackson Oaks Presentation Slides 8-25-2015
 Jackson Oaks/Holiday Lake Presentation 3-29-16