Sewer Improvement Bond Projects

-Lift Stations K and F Upgrade Project.  Design underway by Schaaf & Wheeler with additional enhancements. Construction 2019. 
-Lift Stations J and W. City Council awarded the construction contract to Pacific Infrastructure for $1,153,000 on 4-4-18. Construction nearing completion.
-Monterey Road Sewer Vault Coating Project. Awarded to National Coating for $198,500. Construction complete.
-Sewer Trunk Line Project, Extend the City's sewer trunk line along Monterey Road, starting at Highland/Harding intersection and ending at Renz Road in Gilroy. Working on 65% design plans. See alignment Exhibit.
-Highland Avenue Sewer Upgrade Project. Project Complete.
-Infiltration and Inflow Rehabilitation Project. Replace/repair sewer pipes to reduce storm water infiltration. Construction complete.
-Tennant Sewer Upgrade project. City Council awarded design contract on November 1, 2017 to Mott Macdonald. Design underway for Tennant portion only. Anticipate construction summer 2019.
     
Updated March 19, 2019.