Butterfield Linear Park Extension Project

The Butterfield Linear Park Extension Project extends the current trail on Butterfield Boulevard between East Main Avenue and San Pedro Avenue. The extension connects the existing Class I trail along Butterfield Boulevard at San Pedro Avenue south to Railroad Avenue. The contractor is Terramark General Engineering Contractors, Inc.

This project was completed in Fall 2021. 

Project Updates

Week of August 30, 2021
Phase 2 will continue through mid-September 2021. This phase includes work between Tennant Avenue and Barret Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading and paving of the trail, installing trees, and clean up. 

Phase 3 began on June 21, 2021 and will continue through the end of September 2021. This phase includes work between Barret Avenue and San Pedro Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading and paving of the trail, installing trees, and clean up. 

Week of May 24, 2021
Phase 2 will continue through August of 2021. This phase includes work between Tennant Avenue and Barret Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading and paving of the trail, installing trees, and clean up. This work will require the right lane of northbound Butterfield Boulevard to be closed to traffic during much of this work. 

Phase 3 is scheduled to begin in early June and continue through August of 2021. This phase includes work between Barret Avenue and San Pedro Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading, and paving of the trail, installing trees, and clean up. This work will require the right lane of northbound Butterfield Boulevard to be closed to traffic during much of this work.

Week of May 10, 2021
Phase 2 is scheduled to begin March 29, 2021, and continue through August of 2021. This phase includes work between Tennant Avenue and Barret Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading and paving of the trail, installing trees, and clean up. This work will require the right lane of northbound Butterfield Boulevard to be closed to traffic during much of this work. 

Phase 3 is scheduled to begin mid to late May of 2021 and continue through August of 2021. This phase includes work between Barret Avenue and San Pedro Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading, and paving of the trail, installing trees, and clean up. This work will require the right lane of northbound Butterfield Boulevard to be closed to traffic during much of this work. 

Week of March 29, 2021
Phase 1 of the Butterfield Linear Park Extension is currently underway. This phase includes work between Railroad Avenue to Tennant Avenue and includes grading, preparing the maintenance road, concrete work, asphalt concrete paving, tree planting, and irrigation. Phase 1 will tentatively be completed by March 26, 2021. 

Phase 2 is scheduled to begin March 29, 2021, and continue through August of 2021. This phase includes work between Tennant Avenue and Barret Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading and paving of the trail, installing trees, and clean up. This work will require the right lane of northbound Butterfield Boulevard to be closed to traffic during much of this work. 

Phase 3 is scheduled to begin early April 2021 and continue through August 2021. This phase includes work between Barret Avenue and San Pedro Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading, and paving of the trail, installing trees, and clean up. This work will require the right lane of northbound Butterfield Boulevard to be closed to traffic during much of this work.

Week of March 15, 2021
Phase 1 of the Butterfield Linear Park Extension is currently underway. This phase includes work between Railroad Avenue to Tennant Avenue and includes grading, preparing the maintenance road, concrete work, asphalt concrete paving, tree planting, and irrigation. Phase 1 will tentatively be completed by March 19, 2021. 

Phase 2 is scheduled to begin March 22, 2021, and continue through August of 2021. This phase includes work between Tennant Avenue and Barret Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading and paving of the trail, installing trees, and clean up. This work will require the right lane of northbound Butterfield Boulevard to be closed to traffic during much of this work. 

Phase 3 is scheduled to begin Late-March of 2021 and continue through August of 2021. This phase includes work between Barret Avenue and San Pedro Avenue and includes demolition of the existing curb and gutter, asphalt concrete paving, relocation of curb and gutter, relocation of light pole and traffic light poles, irrigation, backfill, grading and paving of the trail, installing trees, and clean up. This work will require the right lane of northbound Butterfield Boulevard to be closed to traffic during much of this work. 

Week of February 22, 2021
The City of Morgan Hill and Terramark General Engineering Contractors, Inc. will begin the installation of a Class I trail along Butterfield Boulevard between San Pedro Avenue to Railroad Avenue starting January 19, 2021. The work will begin southerly along Railroad Avenue and progress northbound to San Pedro Avenue. The project is tentatively scheduled to be completed by August 2021. The first week of work will be mobilization and set up for work and traffic will be minimally affected.